Idea Locator

The slip corpus

How often do dated commitments (patent expiries, statutory sunsets, regulatory deadlines, plant start-ups) actually happen on the date announced? A category timed to a date inherits that date's reliability. Superseded dates vanish from the record the moment they are superseded; this table keeps them.

Base rates by class

ClassnHeldLateEarlyKilledPendingP(move)Median slip
S1 patent expiry to economic entry42200050%73 mo
S2 statutory sunsets400400100%87 mo
S3 regulatory deadlines162702582%24 mo
S4 plant and project start-ups41200167%87 mo

P(move) counts decided rows only (held, late, early, killed). The corpus is selection-biased toward dates that moved, because routine dates that hold are rarely written about, so every P(move) is an upper bound on the population rate. It is closer to the right conditioning for founders, who only care about dates big enough to build a company against. Download CSV.

Every commitment

ClassCommitmentAnnouncedActual / currentOutcomeSlipMovesSource
S1Lipitor (atorvastatin) US generic entry2011-11-302011-11-30held+0 mo0source M
S1Singulair (montelukast) US generic entry2012-08-032012-08-03held+0 mo0source M
S1Humira (adalimumab) US biosimilar entry
Compound patent expired on schedule; secondary patents and settlements set the economic date.
2016-12-312023-01-31late+73 mo0source H
S1Revlimid (lenalidomide) US volume-unrestricted generic entry
Volume-limited generics from March 2022 under settlements.
2022-03-312026-01-31late+46 mo0source M
S2IRA section 30D clean vehicle credit end date2032-12-312025-09-30early-87 mo1source H
S2IRA 45Y/48E clean electricity credits, wind and solar
Placed-in-service deadline for projects not under construction by July 2026.
2032-12-312027-12-31early-60 mo1source H
S2IRA 45X advanced manufacturing credit, wind components2032-12-312027-12-31early-60 mo1source H
S2IRA section 25D residential clean energy credit2034-12-312025-12-31early-108 mo1source H
S3REAL ID enforcement at TSA checkpoints2008-05-112025-05-07late+204 mo6source H
S3US transition to ICD-10 coding2013-10-012015-10-01late+24 mo2source M
S3US EMV liability shift for automated fuel dispensers
Corrected 2026-10-25: the networks moved the date a second time, from October 2020 to April 2021.
2017-10-012021-04-16late+42 mo2source M
S3GDPR application2018-05-252018-05-25held+0 mo0source H
S3PSD2 strong customer authentication for e-commerce2019-09-142020-12-31late+15 mo1source H
S3DSCSA enhanced security: manufacturers and repackagers2023-11-272025-05-27late+18 mo2source H
S3DSCSA enhanced security: wholesale distributors2023-11-272025-08-27late+21 mo2source H
S3DSCSA enhanced security: dispensers with 26+ staff2023-11-272025-11-27late+24 mo2source H
S3DSCSA enhanced security: small dispensers
Current date not yet reached.
2023-11-272026-11-27pending+36 mo2source H
S3EU Deforestation Regulation: large and medium operators
Postponed in 2024 and again in November 2025; current date not yet reached.
2024-12-302026-12-30pending+24 mo2source H
S3EU Deforestation Regulation: small and micro operators
Corrected 2026-10-25: the original date for small operators was 30 June 2025. Current date not yet reached.
2025-06-302027-06-30pending+24 mo2source M
S3MiCA full application to crypto-asset service providers2024-12-302024-12-30held+0 mo0source H
S3FDA laboratory-developed tests rule, phase 1
Vacated by a federal court in March 2025.
2025-05-06killedkilled—0source H
S3CSRD sustainability reporting, wave 2
Moved by the 2025 'stop-the-clock' directive.
2026-01-012028-01-01pending+24 mo1source M
S3SEC climate-related disclosure rule
Stayed in 2024; the SEC voted to end its defence on 27 March 2025.
2026-01-01killedkilled—1source M
S3EU AI Act high-risk obligations
Moved by the Digital Omnibus per 2026-08-01 research; call C2 tests a second move.
2026-08-022027-12-01pending+16 mo1source M
S4Vogtle unit 3 commercial operation2016-04-012023-07-31late+87 mo5source H
S4Vogtle unit 4 commercial operation2017-04-012024-04-29late+84 mo5source H
S4TSMC Arizona fab 1 volume production
Corrected 2026-10-25: a 2023 announced delay to 2025 was reversed; TSMC reported volume production in Q4 2024.
2024-12-312024-12-31held+0 mo1source M
S4Intel Ohio fab 1 first production
Corrected 2026-10-25: 2030-31 is Intel's current target (announced February 2025), not an actual date.
2025-12-312030-12-31pending+60 mo3source H

Assembled in 2026-08-01 research and corrected on 2026-10-25 where marked. Slip is in whole months from the first announced date to the date in force; a commitment that moved more than once is recorded once at its total displacement, with the number of moves separate. 'Pending' rows have a current date that has not arrived, so their slip is not final.